For this upgrade project, we performed all structural, mechanical and piping, and electrical installation components. We outsourced the electrical works component to a trusted subcontractor. Our fabrication workshop in Gladstone produced the custom pipework, handrails, and platework for the project. Blasting and painting was also performed by Walz in our purpose built facility.
After commissioning, the upgrade increased the plant’s yield by around two percent, delivering approximately 30 tonnes per hour of additional secondary product.
The works incorporated three main areas of the tailings retreat circuit — the Eastern building, the Western building and the secondary product conveyor. A new clarified water pump was also installed to supply the additional demand from the new circuit.
Connecting to the eastern side of CPP1, the Eastern building houses the tailings cyclones, sieve bends, spirals feed sump, and the relocated spirals feed pump.
The Western building connects to a previously existing structure and incorporates the spiral banks, spirals product sump and pump, spirals product cyclone cluster, fine coal centrifuge, and the reject sump and pump.
The secondary product conveyor is fed by the centrifuge, running from the new Western building to transfer product onto the existing steaming coal conveyor.
Australian Gas Infrastructure Group (AGIG) are developing the Hydrogen Park Gladstone project, for the small scale production of hydrogen and injection into the natural gas distribution network as a 10% blended mix. A 175kW NEL electrolyser is the primary hydrogen generation equipment installed, with supporting infrastructure to facilitate the generation and injection of the gas into the distribution grid.
Peak Downs Mine (PDM) identified the Coal Thickener Bridge was at its end of life and required replacing. It supports a range of services including mechanical drives, hydraulics, electrical and control services, flocculent dosing system, compressed air and coal slurry and water pipes. It also provides the suspension of the feed well and thickener raking system.
Fitzroy Coal Management are currently constructing a new underground coal mine, Ironbark No1, located 50km northeast of Moranbah Queensland Walz Group were engaged to complete full Structural, Mechanical and Piping Installation as well as managing an electrical subcontractor to complete the E&I installation works.
Walz were engaged to complete the Structural, Mechanical and Piping construction scope for the main kiln bag filter replacement project, at Cement Australia’s Gladstone plant.
Complete coating patch repairs on gantry stacker girders and associated structural elements from top of rail to 1m below rail level.